Project Stages & Process1/40
Question
CoreYou are the Lead Designer on a traditionally procured project. The client is eager to start on site, but your technical design (Stage 4) is only 80% complete. Can you overlap Stage 4 and 5, and what are the risks if you haven't frozen the design?
Tap to reveal answer